TDOT releases quarterly status report for Washington County road projects

Johnson City Press • Updated Feb 13, 2019 at 5:14 PM

The following is a quarterly status report from the Tennessee Department of Transportation listing highway projects under development or construction in Tennessee’s 6th and 7th House Districts.

• State Route 93

Miscellaneous improvements from Morgan Lane to South of Baileyton Road in Sullivan County, 0.6 miles

The right-of-way and/or utility process is underway.

• Interstate 26

Modify Exit 18 intercharge, 0.8 miles

A contract for construction is scheduled to be let in the 1st Quarter of 2019. 

• State Route 34 US-11E

Miscellaneous safety improvements from Big Limestone Road/McINturff Road to LM 2.02 (RSAR), 0.1 miles 

The engineering is underway

• State Route 34 US-11E

Road safety audit review from Limestone Road to Culver Road, 0.5 miles

The engineering is underway

• State Route 36

Widening the road from State Route 75 in Washington County to Interstate 81 in Sullivan County, 3.5 miles

The engineering is scheduled to begin in the 2nd Quarter of 2019. 

• State Route 93

Preliminary engineering from Interstate 81 to Lone Star Road, 5.4 miles

The right-of-way and/or utility process is underway

• State Route 93

Miscellaneous improvements from north of Davis Road to North of Fire Hall Road, 0.8 miles

The right-of-way and/or utility process is underway

• State Route 353

Bridge replacement over Little Limestone Creek (Old State Route 34)

The engineering is underway.

• State Route 354

Intersection improvements at Bugaboo Springs Road, 0.2 miles

The right-of-way and/or utility process is underway.

• State Route 381, US-321

Signalization at the intersection of Harris Drive

The right-of-way and/or utility process is underway.

• Industrial Access Road

Construction of a new access road serving Clinical Management Concepts, 525 N. State Of Franklin Rd, 0.4 miles. 

The project is currently advertised for the February 8, 2019 bid letting. 

• State Route 36

Miscellaneous safety improvements from near State Route 75 to the Sullivan County Line, 0.590 miles. 

Construction underway with completion expected February 2019. 

 

 

 

 

 

 

 